Feature #5078
Clarification on the ctlModel 1/3
Status:
Resolved
Priority:
Normal
Assignee:
-
Category:
Standard clarification required
Start date:
09/20/2021
Due date:
01/20/2022 (over 2 years late)
% Done:
0%
Estimated time:
ID:
2
Source:
MH
TF Unique ID:
2 # MH
WG10 Proposal:
Estimated Completion:
Discuss in Upcoming Meeting:
No
To discuss in WG10:
No
Short Proposal:
Standard(s):
IEC 61850-7-1 / 7-2 Ed2.1 / 7-5/7-500
Needs More Information:
No
Assigned TF:
Description
What is the purpose of 'ctlModel' at X group level, Y group level respectively? Operator switchgear controls are managed by CSWI LN, so a Select to allow the operator to think twice before Operate is not needed on X group level.
Proposal descriptions
WG 10 needs to decide which task force needs to take a look at all the parts and determine the best approach as to where the clarification(s) needs to be made.
Related issues