Feature #5078

Clarification on the ctlModel 1/3

Added by Carlos Rodriguez del Castillo over 2 years ago. Updated 10 months ago.

Status:
Resolved
Priority:
Normal
Assignee:
-
Category:
Standard clarification required
Start date:
09/20/2021
Due date:
01/20/2022 (over 2 years late)
% Done:

0%

Estimated time:
ID:
2
Source:
MH
TF Unique ID:
2 # MH
WG10 Proposal:
Estimated Completion:
Discuss in Upcoming Meeting:
No
To discuss in WG10:
No
Short Proposal:
Standard(s):

IEC 61850-7-1 / 7-2 Ed2.1 / 7-5/7-500

Needs More Information:
No
Assigned TF:

Description

What is the purpose of 'ctlModel' at X group level, Y group level respectively? Operator switchgear controls are managed by CSWI LN, so a Select to allow the operator to think twice before Operate is not needed on X group level.


Proposal descriptions

WG 10 needs to decide which task force needs to take a look at all the parts and determine the best approach as to where the clarification(s) needs to be made.


Related issues

Related to IEC 61850 User Feedback Task Force - Feature #5079: Clarification on the ctlModel 2/3Resolved09/20/202101/20/2022

Actions
Related to IEC 61850 User Feedback Task Force - Feature #5080: Clarification on the ctlModel 3/3Resolved09/20/202101/20/2022

Actions
Copied to 61850-7-5 and 61850-7-500 - IEC61850-7-5 #6382: Clarification on the ctlModel 1/3New09/20/202101/20/2022

Actions
#1

Updated by Carlos Rodriguez del Castillo over 2 years ago

  • Status changed from New to Triage

Should XCBR (for instance) ctlModel equals to CSWI ctlModel?
ATCC - YLTC? The same?
Action item: Send the question to 7-500 to get more information.

#2

Updated by Vladan Cvejic about 2 years ago

  • Related to Feature #5079: Clarification on the ctlModel 2/3 added
#3

Updated by Vladan Cvejic about 2 years ago

  • Related to Feature #5080: Clarification on the ctlModel 3/3 added
#4

Updated by Vladan Cvejic about 2 years ago

  • Proposal descriptions updated (diff)
  • To discuss in WG10 changed from No to Yes
#5

Updated by Vladan Cvejic about 2 years ago

  • Status changed from Triage to Resolved
  • Discuss in Upcoming Meeting changed from Yes to No
  • To discuss in WG10 changed from Yes to No
  • Standard(s) changed from IEC 61850-7-1 / 7-2 Ed2.1 to IEC 61850-7-1 / 7-2 Ed2.1 / 7-5/7-500

The three ctlModel issues will be addressed by 7-5/7-500 Task Force.

#6

Updated by Carlos Rodriguez del Castillo 11 months ago

  • Needs More Information set to No
#7

Updated by Carlos Rodriguez del Castillo 11 months ago

  • Discuss in Upcoming Meeting changed from No to Yes
#8

Updated by Carlos Rodriguez del Castillo 10 months ago

  • Discuss in Upcoming Meeting changed from Yes to No
#10

Updated by Vladan Cvejic 10 months ago

Also available in: Atom PDF