Issues #6631
tTf1 (mustUnderstand) for the ICT test needs clarification
Due date:
01/09/2024 (about 11 months late)
Discuss in Upcoming Meeting:
No
Clause Reference:
61850 Standard:
6
Triggering Tissue:
Final Decision:
Initial Test Document:
Updated Test Document:
Test Case ID:
tTf1
Closed Reason:
--Not Set---
Triggering Tissue 2:
Triggering Tissue 3:
Description
Copied from #6622:
The test should be modified to test three scenarios.
1) An element has a mustUnderstand in the communication section of the IED being configured, but the IED being configured does not support it.
The ICT should reject the configuration of the IED and provide an error message.
2) An element has a mustUnderstand outside the scope of the IED being configured.
The ICT should import the file.
3) An element has a mustUnderstand element that is in another device but the SCD is configured for use in the IED being configured.
The ICT should reject the configuration of the IED and provide an error message.
Currently (in Ed2.1) mustUnderstand is only used for R-GOOSE and R-SV.