CIM Issues #6357
[GMDM #9] Modeling behind the inverter
Status:
New
Priority:
Normal
Author/Contact Info:
Pat Brown pat@cimpledata.com
Base Release:
17
Solution to be Applied To:
Solution Version:
Solution Applied By:
Completion Date:
CIM Keywords:
Breaking Change:
No
Breaking Change Description:
CIM Impacted Groups:
WG13
Requestor:
Pat Brown
Standard(s):
61970-301, 61970-452, 61968-13
Version:
Clause:
Sub-Clause:
Paragraph:
Table:
Originally Closed in Version:
Origination Date:
Origination ID:
Originally Assigned To:
Description
The GMDM IOP model included a BatteryUnit, PhotovoltaicUnit, and WindPowerElectronicsUnit behind the same residential-sized inverter, i.e., behind a single PowerElectronicsConnection. While theoretically possible, none of the known power flow solvers handle this. PNNL and EPRI both implemented a “virtual battery” concept that might be considered for behind-the-meter or behind-the-inverter resources.
Files
Decision
Oslo 14 June 2023
The issue should be part of the DER discussion