Description

There exist the LNs XCBR/XSWI ("operative model") and the "supervision" LNs SCBR and SOPM. In addition, there are trip and control circuits. The number of instances needed depends on the switchgear technology (single phase switching/tripping and three phase control/tripping). The DOs in the LNs are not always in line with allocated tasks of the LNs. Therefore, a careful consistent and comprehensive remodeling is needed.


Related issues

Copied to 61850-7-5 and 61850-7-500 - IEC61850-7-5 #6377: Update the Switchgear / Breaker ModelNew09/29/2022

Actions
#1

Updated by Christoph Brunner about 1 year ago

  • Source set to WG WS Future
  • Standard(s) set to IEC 61850-7-500
#2

Updated by Christoph Brunner about 1 year ago

  • Status changed from Accepted to In Progress
#3

Updated by Tom Berry about 1 year ago

Note that the 90-3 team is also working on models for supervision of switch-gear

#4

Updated by Vladan Cvejic 4 months ago

#5

Updated by Vladan Cvejic 3 months ago

  • Tracker changed from WG10FutureWork to WG10 Future Work
  • Source deleted (WG WS Future)
  • WG10 Proposal deleted (Allocate to TF 7-5 / 7-500)
  • Discuss in Upcoming Meeting deleted (No)
  • Proposal descriptions updated (diff)
  • Standard(s) deleted (IEC 61850-7-500)
#6

Updated by Vladan Cvejic 3 months ago

  • Discuss in Upcoming Meeting set to No
  • Needs More Information set to No
#7

Updated by Vladan Cvejic 3 months ago

  • Status changed from In Progress to New