Description

There exist the LNs XCBR/XSWI ("operative model") and the "supervision" LNs SCBR and SOPM. In addition, there are trip and control circuits. The number of instances needed depends on the switchgear technology (single phase switching/tripping and three phase control/tripping). The DOs in the LNs are not always in line with allocated tasks of the LNs. Therefore, a careful consistent and comprehensive remodeling is needed.