Project

General

Profile

IEC61850-7-5 #6377

Update the Switchgear / Breaker Model

Added by Vladan Cvejic over 1 year ago.

Status:
New
Priority:
High
Assignee:
-
Start date:
09/29/2022
Due date:
% Done:

0%

Source:
Category:
Not yet categorized
TF 7-5 Project document:
Related TISSUE:

Description

There exist the LNs XCBR/XSWI ("operative model") and the "supervision" LNs SCBR and SOPM. In addition, there are trip and control circuits. The number of instances needed depends on the switchgear technology (single phase switching/tripping and three phase control/tripping). The DOs in the LNs are not always in line with allocated tasks of the LNs. Therefore, a careful consistent and comprehensive remodeling is needed.


Related issues

Copied from IEC TC57 WG10 Future Work - WG10 Future Work #6143: Update the Switchgear / Breaker ModelNew09/29/2022

Actions

Also available in: Atom PDF