Project

General

Profile

Improvement #610

Mapping of another phases system description to the generic phases phsA, phsB, phsC

Added by Carlos Rodriguez del Castillo almost 4 years ago. Updated over 1 year ago.

Status:
Resolved
Priority:
Normal
Assignee:
-
Category:
Standard extension required
Start date:
10/07/2020
Due date:
04/07/2021 (over 3 years late)
% Done:

0%

Estimated time:
ID:
2
Source:
RTE
TF Unique ID:
2 # RTE
WG10 Proposal:
Estimated Completion:
IEC 61850-6 edition 3
Discuss in Upcoming Meeting:
No
To discuss in WG10:
No
Short Proposal:

To include the definition in Substation->VoltageLevel section

Standard(s):

IEC 61850-6

Needs More Information:
No
Assigned TF:

Description

Example : how to map system 0-4-8 or 3-7-11 to phsA-phsB-phsC.
Helpful for maintenance and exploitation of the system.


Files

20210326-RTE Use cases - 610.docx 20210326-RTE Use cases - 610.docx 16.7 KB Use case explanation Carlos Rodriguez del Castillo, 05/11/2021 10:13 AM

Proposal descriptions

To be discussed inside WG10 in tems of evolution to edition 3.


Related issues

Copied to IEC TC57 WG10 Future Work - WG10 Future Work #5939: Mapping of another phases system description to the generic phases phsA, phsB, phsCNew10/07/2020

Actions

Also available in: Atom PDF