Issues #7028
There is no conformance procedure/block for TimeOperated Control
Due date:
11/12/2024 (11 days late)
Discuss in Upcoming Meeting:
No
Clause Reference:
61850 Standard:
Triggering Tissue:
Final Decision:
Initial Test Document:
Updated Test Document:
Test Case ID:
Closed Reason:
--Not Set---
Triggering Tissue 2:
Triggering Tissue 3:
Description
In order to perform coordinated switching, without GOOSE, TimeOperated control is the mechanism to achieve this. In the particular use case, under development, coordination of an LTC and Capacitor Bank Controller may be required for Volt/Var and PF control.
We need to have conformance test procedures and a conformance block (certificate change) for this feature.