There is no conformance procedure/block for TimeOperated Control

Added by Herbert Falk about 1 month ago. Updated 11 days ago.

Status:
Resolved
Priority:
Normal
Assignee:
Due date:
11/12/2024 (11 days late)
Discuss in Upcoming Meeting:
No
Clause Reference:
61850 Standard:
Triggering Tissue:
Final Decision:
Initial Test Document:
Updated Test Document:
Test Case ID:
Closed Reason:
--Not Set---
Triggering Tissue 2:
Triggering Tissue 3:

Description

In order to perform coordinated switching, without GOOSE, TimeOperated control is the mechanism to achieve this. In the particular use case, under development, coordination of an LTC and Capacitor Bank Controller may be required for Volt/Var and PF control.

We need to have conformance test procedures and a conformance block (certificate change) for this feature.

#1

Updated by Richard Schimmel about 1 month ago

TimeActivedOperate is a conditional service in block 12a, 12b, 12c and 12d. The corresponding test cases are: sDOns4, sDOns5, sSBOns4, sSBOns5, sDOes4, sDOes5, sSBOes4, sSBOes5. I propose to reject this issue.

#2

Updated by Herbert Falk about 1 month ago

That still doesn’t make the Redmine Database searchable for time activated control.

I agree if the test cases are there, then no new test cases are needed but we need a better way to search Redmine…

#3

Updated by IEC 61850 TPWG 25 days ago

  • Due date set to 11/12/2024
  • Status changed from New to In Progress
  • Assignee set to Herb Falk

This is a redmine issue? Discuss with Herb.

#4

Updated by IEC 61850 TPWG 11 days ago

  • Status changed from In Progress to Resolved

Herb to add checkbox in the certificate database to indicate devices that have been tested for TimeActivatedOperate