Issues #6875

Update Client certificate template following the server certificate template

Added by Andreas Hetz 3 months ago. Updated 23 days ago.

Status:
Resolved
Priority:
Normal
Due date:
10/29/2024 (23 days late)
Discuss in Upcoming Meeting:
No
Clause Reference:
61850 Standard:
6, 7-1, 7-2, 7-3, 7-4, 8-1, 8-2, 9-2, 9-3
Triggering Tissue:
Final Decision:
Initial Test Document:
Updated Test Document:
Test Case ID:
Closed Reason:
--Not Set---
Triggering Tissue 2:
Triggering Tissue 3:

Description

Page 154:
Issue: "The CLIENT has not been shown to be non-conforming to:"
Proposal: "The CLIENT product has not been shown to be non-conforming to:"

Issue: The table shows 1 Basic Exchange
Proposal: The table should show 1a Basic Exchange

Issue: "The Certificate includes a summary...." (typo=
Proposal: "The certificate includes a summary..."

Page 155:
Issue: The UCA logo is missing in the upper right corner
Proposal: Put it in

Issue: "..., and the original paper copy of the...."
Proposal: "...- and the original [paper/archived] copy of the..."

Issue: "..., product’s protocol, model and technical issue implementation..."
Proposal: "..., product’s protocol, model and tissues implementation ..."

#1

Updated by Andreas Hetz 3 months ago

The upper-described issues have been raised against an older version, still they are still valid for the latest "August" version.

August Version Page 113:
Issue: 36 SCD Export (../6)
Proposal 36 SCD Export (../7)

#2

Updated by IEC 61850 TPWG 3 months ago

  • Due date set to 10/01/2024
  • Status changed from New to In Progress
  • Assignee set to Andreas Hetz
  • Priority changed from Low to Normal
  • 61850 Standard 6, 7-1, 7-2, 7-3, 7-4, 8-2, 9-2, 9-3 added
#3

Updated by IEC 61850 TPWG about 2 months ago

  • Due date changed from 10/01/2024 to 10/29/2024

Accepted

#4

Updated by IEC 61850 TPWG 23 days ago

  • Status changed from In Progress to Resolved
  • Assignee changed from Andreas Hetz to Richard Schimmel

Also available in: Atom PDF