Issues #6835
Impact of publication of IEC 61850-6 Edition 2.2 on Edition 2.1 certification of Server/Client and Tools
Status:
In Progress
Priority:
Normal
Assignee:
-
Due date:
12/10/2024 (11 days late)
Triggering Tissue:
Description
With the release of IEC 61850-6 Ed2.2,
What does change for the Ed2.1 Certificate of
- Server
- Client
?
What does change for the Ed2.2 Certificate of
- ICT
- SCT
?
Server / Client: modify the testing procedures so that either SCL Ed2.1 or SCL Ed2.2 are used for ICD/IID export, SCD Import, and modify certificate template to show which SCL release was used?
ICT/SCT: TP specifies Ed2.2 and certificate as well? Ed2.1 Tooling test procedure end of certification?
Files
Updated by IEC 61850 TPWG about 2 months ago
- Due date set to 11/12/2024
- Status changed from New to In Progress
To be reviewed after WG10 discussion.
Updated by Thierry Dufaure about 2 months ago
See attached recommendations from WG10 Meeting in Nanjing.
Updated by IEC 61850 TPWG about 1 month ago
- Due date changed from 11/12/2024 to 12/10/2024
Richard to form TF to work on the SCT procedure updates.
ICT being able to validate against schema may be an issue? Needs to be tested.