Project

General

Profile

WG10 Future Work #6578

Extension of the AddCause required to reflect communication issues in multi level control

Added by Vladan Cvejic 11 months ago. Updated 8 months ago.

Status:
New
Priority:
Normal
Assignee:
-
Start date:
04/01/2022
Due date:
% Done:

0%

Estimated time:
Source:
TF 61850-80-6
TF Unique ID:
4 # 80-6
WG10 Proposal:
Discuss in Upcoming Meeting:
No
Short Proposal:
Standard(s):

IEC 61850-7-2; IEC 61850-8-1, 80-6

Needs More Information:
Yes
Assigned TF:
61850-7-2, 61850-8-1, 61850-80-6 Substation to Control Centre Communication
Target edition:
Next

Description

During the review of the control model of the Proxy/Gateway in IEC 61850-80-6 we found that the existing enumeration for the AddCause does not include values to reflect the situation where the Proxy/Gateway issues a negative confirmation to the control center client when the communication with the underlying IED that executes the command is disturbed, or the connection to the device is lost.
This issue is not only relevant for the communication to the control center, but on always when the control action involves more than one communication level, e.g. Substation Scada to Breaker IED via an bay controller IED.
Attached is a slide set which explains the need and proposes the new enumerated values for the AddCause.


Files

AddCause.pdf View AddCause.pdf 758 KB Use case description Andreas Ostermeier, 04/01/2022 09:25 AM

Proposal descriptions

TF IEC 61850-80-6 proposed to extend the enumeration for the AddCause with 2 new ACSI values

ACSI value MMS value
Communication-timeout 28
Communication-lost 29


Related issues

Copied from IEC 61850 User Feedback Task Force - Feature #5336: Extension of the AddCause required to reflect communication issues in multi level controlIn ProgressAndreas Ostermeier04/01/2022

Actions
#1

Updated by Vladan Cvejic 11 months ago

  • Copied from Feature #5336: Extension of the AddCause required to reflect communication issues in multi level control added
#2

Updated by Vladan Cvejic 8 months ago

  • Target edition changed from Not assigned to Next
  • Assigned TF 61850-7-2, 61850-8-1, 61850-80-6 Substation to Control Centre Communication added

Also available in: Atom PDF