Issues #6526
Revision 0.7 (final draft) should be 1.0
Due date:
11/14/2023
Discuss in Upcoming Meeting:
No
Clause Reference:
61850 Standard:
6
Triggering Tissue:
Final Decision:
Initial Test Document:
Updated Test Document:
Test Case ID:
Closed Reason:
--Not Set---
Triggering Tissue 2:
Triggering Tissue 3:
Description
The version/revision need to be updated to 1.0 (or 1.1).
Also the revision table (page 2) need to be removed in the final version.
Updated by Richard Schimmel about 1 year ago
- Status changed from New to In Progress
See draft version 1.1 e-mailed 28 Sept to the TPWG.
Updated by IEC 61850 TPWG about 1 year ago
- Due date set to 10/17/2023
- Assignee set to Richard Schimmel
Accepted.