New LN of group L (as "LTED") to represent the dynamic topology of the substation.

Added by Carlos Rodriguez del Castillo about 3 years ago. Updated 12 months ago.

Status:
Resolved
Priority:
Normal
Category:
Standard extension required
Start date:
10/23/2020
Due date:
% Done:

0%

Estimated time:
ID:
15
Source:
RTE
TF Unique ID:
15 # RTE
WG10 Proposal:

Was addressed in last WG10 plenary meeting. Decision: It has to be addressed in a Task Force. In order to create the TF, we have to wait for another existent TF to finished. Open: WG17 or WG10 to lead the work.

Estimated Completion:
Need to wait for a TF finalization to start this new one.
Discuss in Upcoming Meeting:
No
To discuss in WG10:
No
Short Proposal:

New task force to address the work.

Standard(s):
Needs More Information:
No
Assigned TF:

Description

Details:
Some functions need to know the current topology of the substation.
For doing that,
- 1 LN LTED is instanciated for each feeder connected to the busbar and for each busbar segment.
- ElNodeRef indicates the reference number of the electrical node of the busbar to which the LN is associated, calculated on the base of its actual topology (disconnector and circuit breaker position).
- ElNodeNum indicates the total number of electrical nodes into which a busbar is splitted on the base of its actual topology (disconnector and circuit breaker position).
- ElNodeVTRef is used by the LD publishing voltage information (SV or PhV). Only one LD can adopt the number of the Electrical Node. This LD published the busbar voltage reference for corresponding electrical node, indicating if this voltage is to be used as voltage reference for an Electrical Node. If not, its value is set to zero.

Argument: Needed for some PACS functions.


Related issues

Copied to IEC TC57 WG10 Future Work - WG10 Future Work #5943: New LN of group L (as "LTED") to represent the dynamic topology of the substation.NewCarlos Rodriguez del Castillo10/23/2020

Actions
#1

Updated by Carlos Rodriguez del Castillo about 3 years ago

  • Status changed from New to In Progress
#2

Updated by Carlos Rodriguez del Castillo about 3 years ago

  • Status changed from In Progress to New
#3

Updated by Carlos Rodriguez del Castillo about 3 years ago

  • Status changed from New to Resolved
  • Short Proposal set to New task force to address the work.
  • WG10 Proposal set to Was addressed in last WG10 plenary meeting. Decision: It has to be addressed in a Task Force. In order to create the TF, we have to wait for another existent TF to finished. Open: WG17 or WG10 to lead the work.
  • Estimated Completion set to Need to wait for a TF finalization to start this new one.

It is an open question which WG will lead the work: WG17 or WG10.

#4

Updated by Carlos Rodriguez del Castillo about 3 years ago

  • Start date changed from 10/07/2020 to 10/23/2020
#5

Updated by Carlos Rodriguez del Castillo about 3 years ago

  • Assignee set to Carlos Rodriguez del Castillo
  • Discuss in Upcoming Meeting changed from Yes to No
  • To discuss in WG10 set to No

2021-03-02: Carlos check with Christoph Brunner to put this need in the Future Work spreadsheet.

#6

Updated by Vladan Cvejic over 1 year ago

  • Copied to WG10 Future Work #5943: New LN of group L (as "LTED") to represent the dynamic topology of the substation. added
#7

Updated by Carlos Rodriguez del Castillo 12 months ago

  • Needs More Information set to No