CIM Issues #5845
Propose Flexible Ramping Up (FRU or RampUp) and Flexible Ramping Down (FRD or RampDown). Update descriptions of all enum values.
Description
Propose Flexible Ramping Up (FRU or RampUp) and Flexible Ramping Down (FRD or RampDown). Update descriptions of all enum values.
Proposed Solution
Propose the following updated descriptions for the enums:
EN: Energy generally priced per kWh or MWh
LFU: Load following up (power injection) generally priced per kW or MW
LFD: Load following down (power withdrawl) generally priced per kW or MW
RU: Frequency Regulation Service (energy injection)
RD: Frequency Regulation Service (energy withdrawl)
REG: Frequency Regulation Service (injection and/or withdrawl)
SR: Spinning Reserve or Contingency Reserve generally priced per kWh or MWh
NR: Non-spinning Reserve or Replacement Reserve generally priced per kWh or MWh
RC: Residual Unit Commitment (Resources with available capacity for a forward market such as Day Ahead. An award indicates they are needed for resource adequacy (i.e. reliability) purposes.)
RPU: RampUp: Power injection generally priced per kW or MW
RPD: RampDown: Power withdrawl generally priced per kW or MW
RMU: Regulation Mileage Up
RMD: Regulation Mileage Down
PL: Power Limit (see use case from Peter F. "Use Case Power Limit.docx")
Decision
3/3/2022: Team agreed to use the updated descriptions, adding the new enums RPU, RPD, RMU, RMD.
Request Peter to attend an upcoming call to address the Power Limit use case as a market product. Pull this use case to a new issue. 16_0141