Project

General

Profile

Issues #5926

Review ICT TP

Added by IEC 61850 TPWG over 1 year ago. Updated over 1 year ago.

Status:
Resolved
Priority:
Normal
Assignee:
Due date:
11/15/2022 (about 17 months late)
Discuss in Upcoming Meeting:
No
Clause Reference:
61850 Standard:
Triggering Tissue:
Final Decision:
Initial Test Document:
Updated Test Document:
Test Case ID:
Closed Reason:
Test Procedure Update
Triggering Tissue 2:
Triggering Tissue 3:
#1

Updated by Joel Greene over 1 year ago

  • Due date set to 09/06/2022
  • Proposal descriptions updated (diff)
#2

Updated by IEC 61850 TPWG over 1 year ago

  • File UCATestProcedures_Server_ICT_Ed2Amd1_DRAFT05.docx added
#3

Updated by IEC 61850 TPWG over 1 year ago

  • Due date changed from 09/06/2022 to 09/20/2022
  • Status changed from New to In Progress
  • Start date changed from 08/09/2022 to 09/20/2022
#4

Updated by IEC 61850 TPWG over 1 year ago

  • Due date changed from 09/20/2022 to 10/14/2022

sMdl27 to be updated by Richard. Camille to provide comments by EOW.

Otherwise, approved for release.

#5

Updated by IEC 61850 TPWG over 1 year ago

  • File deleted (UCATestProcedures_Server_ICT_Ed2Amd1_DRAFT05.docx)
#6

Updated by IEC 61850 TPWG over 1 year ago

  • Tracker changed from Improvement to Issues
  • Project changed from General Testing Issues to SCL Tooling
  • Due date changed from 10/14/2022 to 11/01/2022
  • Start date deleted (09/20/2022)
  • Proposal descriptions updated (diff)
  • Discuss in Upcoming Meeting set to No
  • Closed Reason --Not Set--- added

To be published.

#7

Updated by IEC 61850 TPWG over 1 year ago

  • Due date changed from 11/01/2022 to 11/15/2022
  • Assignee set to Joel Greene

Ready to publish, no outstanding comments.

Any further issues to be entered in Redmine.

#8

Updated by IEC 61850 TPWG over 1 year ago

  • Status changed from In Progress to Resolved
  • Closed Reason Test Procedure Update added
  • Closed Reason deleted (--Not Set---)

Also available in: Atom PDF