Project

General

Profile

CIM Issues #5922

New association between energyMarket & Process and Timeseries

Added by Becky Iverson over 1 year ago. Updated 6 months ago.

Status:
Closed
Priority:
Normal
Author/Contact Info:
Alvaro Marciel
Base Release:
iec61970cim18v02_iec61968cim14v00_iec62325cim04v14
Solution to be Applied To:
Solution Version:
iec61970cim18v02_iec61968cim14v00_iec62325cim04v15
Solution Applied By:
Becky Iverson
Completion Date:
10/10/2023
CIM Keywords:
Breaking Change:
Breaking Change Description:
CIM Impacted Groups:
WG16
Requestor:
Standard(s):
Version:
Clause:
Sub-Clause:
Paragraph:
Table:
Originally Closed in Version:
Origination Date:
Origination ID:
Originally Assigned To:

Description

At ENTSO-E there are multiple processes that are run at different timeframes. For example Capacity Calculation Process can be run for Long-Term, D-2, Day-Ahead, Intraday and Real-Time (15 min resolution). However it is not possible to define the timeframe of a process in the current version. There are also some cases in which a timeframe could be defined for certain businessTypes. For example, we could have Day-Ahead or Intraday market prices. Currently in both ESMP process and businessType codelist there is a mix of timeframes, business and processes. In order to have a better attribute granularity, ENTSO-E is interested in the introduction of the EnergyMarket class in ESMP.


Proposed Solution

Move EnergyMarket from package MarketPlan to MarketCommon. Add new associations between Process and EnergyMarket and between TimeSeries and EnergyMarket.


Release Notes

EnergyMarket moved to MarketCommon package
Association added; EnergyMarket -> Process
Association added; EnergyMarket -> TimeSeries
EnergyMarket added attribute timeframe

Also available in: Atom PDF