CIM Issues #6779
Expand ScheduleKind to include Generation
Status:
Closed
Priority:
Normal
Author/Contact Info:
Base Release:
Solution to be Applied To:
iec61970cim18v02_iec61968cim14v00_Market04v16
Solution Version:
iec61970cim18v02_iec61968cim14v00_Market04v16
Solution Applied By:
Becky Iverson
Completion Date:
CIM Keywords:
Breaking Change:
Breaking Change Description:
CIM Impacted Groups:
WG16
Requestor:
Standard(s):
Version:
Clause:
Sub-Clause:
Paragraph:
Table:
Originally Closed in Version:
Origination Date:
Origination ID:
Originally Assigned To:
Description
Add:
- generationIncrease = The resource operates primarily as a variable generation resource, where a positive amount corresponds to a relative generation increase.
- generationDecrease = The resource operates primarily as a variable generation resource, where a positive amount corresponds to a relative generation reduction.
Proposed Solution
Add two new enum values to the enumeration ScheduleKind:
generationIncrease
gnerationReduction
Decision
The team agreed to add the two new enumeration values.
Release Notes
Added two new enum values to the enumeration ScheduleKind:
generationIncrease
gnerationReduction