Project

General

Profile

CIM Issues #6779

Expand ScheduleKind to include Generation

Added by Scott Coe 3 months ago. Updated about 1 month ago.

Status:
Review
Priority:
Normal
Author/Contact Info:
Base Release:
Solution to be Applied To:
iec61970cim18v02_iec61968cim14v00_Market04v16
Solution Version:
iec61970cim18v02_iec61968cim14v00_Market04v16
Solution Applied By:
Becky Iverson
Completion Date:
CIM Keywords:
Breaking Change:
Breaking Change Description:
CIM Impacted Groups:
WG16
Requestor:
Standard(s):
Version:
Clause:
Sub-Clause:
Paragraph:
Table:
Originally Closed in Version:
Origination Date:
Origination ID:
Originally Assigned To:

Description

Add:
- generationIncrease = The resource operates primarily as a variable generation resource, where a positive amount corresponds to a relative generation increase.
- generationDecrease = The resource operates primarily as a variable generation resource, where a positive amount corresponds to a relative generation reduction.


Proposed Solution

Add two new enum values to the enumeration ScheduleKind:
generationIncrease
gnerationReduction


Decision

The team agreed to add the two new enumeration values.


Release Notes

Added two new enum values to the enumeration ScheduleKind:
generationIncrease
gnerationReduction

#1

Updated by Becky Iverson about 1 month ago

  • Status changed from New to Open
  • Solution to be Applied To set to iec61970cim18v02_iec61968cim14v00_Market04v16
  • Proposed Solution updated (diff)
  • Decision updated (diff)
#2

Updated by Becky Iverson about 1 month ago

  • Status changed from Open to In Progress
#3

Updated by Becky Iverson about 1 month ago

  • Status changed from In Progress to Review
  • Solution Version set to iec61970cim18v02_iec61968cim14v00_Market04v16
  • Solution Applied By set to Becky Iverson
#4

Updated by Becky Iverson about 1 month ago

  • Release Notes updated (diff)

Also available in: Atom PDF