Project

General

Profile

CIM Issues #6744

CrewStatusKind enumeration is missing values for deassignment

Added by Martin Miller 8 months ago. Updated 8 months ago.

Status:
New
Priority:
Normal
Author/Contact Info:
martin.miller@hitachienergy.com
Base Release:
Solution to be Applied To:
Solution Version:
Solution Applied By:
Completion Date:
CIM Keywords:
61968-Common
Breaking Change:
Breaking Change Description:
CIM Impacted Groups:
WG14
Requestor:
martin.miller@hitachienergy.com
Standard(s):

61968-3

Version:
3
Clause:
C.6
Sub-Clause:
Paragraph:
Table:
C6
Originally Closed in Version:
Origination Date:
Origination ID:
Originally Assigned To:

Description

The current CrewStatusKind enumeration only contains entries for assignment of crews and the only value (fieldComplete) that represents the deassignment of a crew also represents the completion of work. It is missing any entries that represent the deassignment of a crew without completement of work.

At a minimum the enumeration needs an additional value to represent the concept of "Deassigned" which means that "the crew is no longer working on the outage in the field, without the outage being corrected".
Ideally, there would also be a second additional value to represent the concept of "Rejected" which means that "the crew has refused an assignment."


Proposed Solution

At a minimum the enumeration needs an additional value to represent the concept of "Deassigned" which means that "the crew is no longer working on the outage in the field, without the outage being corrected".
Ideally, there would also be a second additional value to represent the concept of "Rejected" which means that "the crew has refused an assignment."

Also available in: Atom PDF