CIM Issues #6245
It is not possible to convey that an UnplannedOutage is frozen (prediction is suspended).
Status:
New
Priority:
Normal
Author/Contact Info:
martin.bass@hitachienergy.com
Base Release:
61968-3 edition 3
Solution to be Applied To:
61968-3 edition 4
Solution Version:
Solution Applied By:
Completion Date:
CIM Keywords:
61968-Operations
Breaking Change:
No
Breaking Change Description:
CIM Impacted Groups:
WG14
Requestor:
Standard(s):
Version:
Clause:
Sub-Clause:
Paragraph:
Table:
Originally Closed in Version:
Origination Date:
Origination ID:
Originally Assigned To:
Description
Most commercial outage management systems support this concept (at least three that we are aware of). It is used to stop an unplanned outage from predicting to a different location when additional trouble tickets are received. An unplanned outage can be frozen due to the passage of time. An unplanned outage can also be frozen if the outage prediction has been overridden by a user, to prevent the outage being re-predicted at its original location.
Proposed Solution
Add 'frozen' to the enumeration of OutageKind (current values are predicted, confirmed, partiallyRestored, restored, closed).