Project

General

Profile

Issues

Filters

Apply Clear

# Project Tracker ID Source Status Priority Standard(s) Subject Updated
424 IEC 61850 User Feedback Task Force Support 15 ENTSO-E In Progress Normal

6

Vendor Tools shall allow (vendor independant) Integration tools doing engineering based on ICD Files, thus allowing them to in 02/03/2021 02:49 PM Actions
417 IEC 61850 User Feedback Task Force Support 9 ENTSO-E In Progress Normal

6-100

There is no mechanism proposed by the Standard to positively identify data points in the data model. For instance PTOC can refer 02/03/2021 02:49 PM Actions
439 IEC 61850 User Feedback Task Force Bug 2 Vattenfall In Progress High

IEC 61850-6

How to add utility process name to DOs 02/11/2021 06:37 AM Actions
578 IEC 61850 User Feedback Task Force Feature 50 ENTSO-E In Progress Normal

IEC 61850-7-4

Busbar protection: End Fault protection - model definition required. 02/11/2021 07:10 AM Actions
576 IEC 61850 User Feedback Task Force Feature 48 ENTSO-E In Progress Normal

IEC 61850-7-4

Distance protection: Distance protection - 1 phase and 3 phase zone extension signals are missing 02/11/2021 07:11 AM Actions
575 IEC 61850 User Feedback Task Force Feature 47 ENTSO-E In Progress Normal

IEC 61850-7-4

Protection scheme: Reversal current logic LN/DO/DA missing 02/11/2021 07:13 AM Actions
574 IEC 61850 User Feedback Task Force Feature 46 ENTSO-E In Progress Normal

IEC 61850-7-4

Protection scheme: Weak end infeed (1 phase and 2/3 phase operate missing) 02/11/2021 07:13 AM Actions
573 IEC 61850 User Feedback Task Force Feature 45 ENTSO-E In Progress Normal

IEC 61850-7-4

Tap Changer Supervision: Tap discrepancy (3 pole transformer case) 02/11/2021 07:14 AM Actions
438 IEC 61850 User Feedback Task Force Feature 1 Vattenfall In Progress Normal

IEC 61850-6 (-100)

The engineering-process is well defined for a green field / new IEC 61850 substation but needs clarification for refurbishment 02/11/2021 07:59 AM Actions
409 IEC 61850 User Feedback Task Force Feature 4.1 ENTSO-E In Progress Normal Too loose or non existing guideline for organization of structure tree (construction of each LD, LN etc) 02/11/2021 08:00 AM Actions
583 IEC 61850 User Feedback Task Force Support 55 ENTSO-E Triage Normal

IEC 61850-7-4

Autoreclosure: Autoreclosure - 3ph closing command missing 02/16/2021 04:00 AM Actions
566 IEC 61850 User Feedback Task Force Support 38 ENTSO-E Triage Normal

IEC 61850-7-420

S/S related applications: Diesel aggregat alarm 02/16/2021 04:08 AM Actions
559 IEC 61850 User Feedback Task Force Support 31 ENTSO-E Triage Normal

IEC 61850-7-4

Busbar protection: ARC detection protection 02/16/2021 04:09 AM Actions
558 IEC 61850 User Feedback Task Force Support 30 ENTSO-E Triage Normal

IEC 61850-7-4

Busbar protection (BBP): Diff/Kirchoff BBP 02/16/2021 04:10 AM Actions
582 IEC 61850 User Feedback Task Force Support 54 ENTSO-E Triage Normal

IEC 61850-7-4, 7-5

Synchrocheck: Synchrocheck - missing signals 02/16/2021 04:11 AM Actions
581 IEC 61850 User Feedback Task Force Support 53 ENTSO-E Triage Normal

IEC 61850-7-4, 7-5

S/S related applications: Disturbance recorder - communication session active 02/16/2021 04:11 AM Actions
569 IEC 61850 User Feedback Task Force Support 41 ENTSO-E Triage Normal

IEC 61850-7-4

S/S related applications: Access security system 02/16/2021 04:13 AM Actions
619 IEC 61850 User Feedback Task Force Feature 15 RTE Resolved Normal New LN of group L (as "LTED") to represent the dynamic topology of the substation. 03/02/2021 09:29 AM Actions
623 IEC 61850 User Feedback Task Force Feature 19 RTE In Progress Normal New LN of group L (as "LPLE") representing a group of LED 03/02/2021 09:42 AM Actions
624 IEC 61850 User Feedback Task Force Support 21 RTE Triage Normal

IEC 61850-6

Clarification of using of ValKind, ValImport. 03/02/2021 09:44 AM Actions
625 IEC 61850 User Feedback Task Force Improvement 22 RTE Resolved Normal

IEC 61850-7-4

LN RADR evolution 03/02/2021 09:49 AM Actions
626 IEC 61850 User Feedback Task Force Improvement 23 RTE In Progress Normal

IEC 61850-6

Extension of P-type to describe connexion type (PhysCon) 03/02/2021 09:51 AM Actions
627 IEC 61850 User Feedback Task Force Feature 29 RTE Resolved Normal

IEC 61850-7-4

Activation and deactivation of a function by configuration. 03/02/2021 09:53 AM Actions
434 IEC 61850 User Feedback Task Force Support 25 ENTSO-E In Progress Normal Freedom of choice what IEC 61850 services are to be tested seem too open. The vendor can select exactly what UCA accredited test 04/02/2021 01:30 PM Actions
647 IEC 61850 User Feedback Task Force Support 57 ENTSO-E Resolved Normal

IEC 61850-7-5, IEC61850-7-500

Single phase and multi phase trip indication for the autorecloser 04/13/2021 09:42 AM Actions
(1-25/1781) Per page: 25, 50, 100

Also available in: Atom CSV PDF