6446 IEC TC57 WG10 Future Work WG10 Future Work WG10 Fall workshop New Low

TR IEC 61850-7-500

SCL Modelling of Fault Measurements (RFMX) 02/08/2024 02:12 AM Actions
6165 IEC TC57 WG10 Future Work WG10 Future Work Tissue DB New Normal

TR IEC 61850-7-500

https://iec61850.tissue-db.com/tissue/1844 - Implementation of SumSwARs in 3-phase circuit breaker inaccurate 10/26/2023 05:01 AM Actions
6162 IEC TC57 WG10 Future Work WG10 Future Work Tissue DB New Normal

TR IEC 61850-7-500

https://iec61850.tissue-db.com/tissue/1803 - Mechanical Blocking of 3 way switches 10/26/2023 05:07 AM Actions
6155 IEC TC57 WG10 Future Work WG10 Future Work Tissue DB New Normal

TR IEC 61850-7-500

https://iec61850.tissue-db.com/tissue/1706 Missing LN for Miniature Circuit Breaker (MCB) 10/26/2023 05:19 AM Actions
6411 IEC TC57 WG10 Future Work WG10 Future Work WG10 Fall workshop New Urgent

TR IEC 61850-7-500, TR IEC 61850-90-3

Update the Model of Circuit Breaker/Disconnector Switch 10/26/2023 03:08 AM Actions
6143 IEC TC57 WG10 Future Work WG10 Future Work New High

TR IEC 61850-7-500, TR IEC 61850-90-3

Update the Switchgear / Breaker Model 10/26/2023 03:50 AM Actions
6441 IEC TC57 WG10 Future Work WG10 Future Work WG10 Fall workshop New Normal

TR IEC 61850-90-14

Extensions to "Z" Logical Nodes (e.g. ZBAT) 10/26/2023 04:10 AM Actions
6160 IEC TC57 WG10 Future Work WG10 Future Work Tissue DB New Normal

TR IEC 61850-90-29

https://iec61850.tissue-db.com/tissue/1796 LPHD.PwrSupAlm as Omulti 10/26/2023 05:13 AM Actions
6427 IEC TC57 WG10 Future Work WG10 Future Work WG10 Fall workshop New Normal

TR IEC 61850-90-3

New Logical Nodes - Battery Charger 10/26/2023 04:31 AM Actions
6159 IEC TC57 WG10 Future Work WG10 Future Work Tissue DB New Normal

TR IEC 61850-90-3

https://iec61850.tissue-db.com/tissue/1789 SCBR - Coilxxx-Data-Objects shall be Omulti 10/26/2023 05:14 AM Actions
6432 IEC TC57 WG10 Future Work WG10 Future Work WG10 Fall workshop New Normal

TR IEC 61850-90-30

SCL Engineering Lifecycle, Types and Security for SCL files and Elements 10/26/2023 04:26 AM Actions
6417 IEC TC57 WG10 Future Work WG10 Future Work WG10 Fall workshop New Normal

TR IEC 61850-90-4

SCL Modelling of the Communication Network and All its Components 10/26/2023 04:40 AM Actions
6423 IEC TC57 WG10 Future Work WG10 Future Work WG10 Fall workshop New Normal

TS IEC 61850-80-7

SCL Control Block 10/26/2023 04:32 AM Actions
438 IEC 61850 User Feedback Task Force Feature 1 Vattenfall Resolved Normal

IEC 61850-4

The engineering-process is well defined for a green field / new IEC 61850 substation but needs clarification for refurbishment 12/05/2023 08:26 AM Actions
5122 IEC 61850 User Feedback Task Force Feature 1 TF 61850-80-6 Resolved Normal

IEC 61850-90-28

New LN in LN group L to reflect the status of TPAA between Proxy/Gateway and IED 06/05/2023 01:58 AM Actions
554 IEC 61850 User Feedback Task Force Support 1 H30 Resolved Normal Performance requirement for SV and implications to Protection applications 05/09/2023 09:32 AM Actions
519 IEC 61850 User Feedback Task Force Support 1 UFTF Resolved Normal

80-7

Optionality in DOI NamPlt, PhyNam resp. in ICD/IID file: IED.manufacturer, .IED.type, makes a device recognition in a machine to 06/05/2023 01:58 AM Actions
3098 IEC 61850 User Feedback Task Force Improvement 1 WG17 In Progress Normal Need to Change 8-1 to allow multiple DOs to be written 03/29/2022 09:36 AM Actions
633 IEC 61850 User Feedback Task Force Improvement 1 ZIV Resolved Normal

IEC 61850-4

Initial values of paramRev and valRev 11/21/2023 09:09 AM Actions
3099 IEC 61850 User Feedback Task Force Improvement 1 TissueDB Resolved Normal

IEC 61850-7-4

IEC61850.Tissue #1756 Event driven schedules – Extend description 06/05/2023 01:58 AM Actions
5321 IEC 61850 User Feedback Task Force Improvement 1 WG17 Resolved Normal

IEC 61850-7-4,7-5

Schedules - allow 3 values per time point 06/05/2023 01:58 AM Actions
5091 IEC 61850 User Feedback Task Force Feature 10 H30 Resolved Normal

IEC 61850-2

Devices types/acronyms 06/05/2023 01:58 AM Actions
5086 IEC 61850 User Feedback Task Force Feature 10 MH Resolved Normal

IEC 61850-7-4 Ed2.1 ,7-5

Clarifications on the local/remote concept 6/8 06/05/2023 01:58 AM Actions
612 IEC 61850 User Feedback Task Force Feature 11 RTE Resolved Normal

IEC 61850-7-4

Need to create a new LN of group P (Protection), as "PCDP" to represent the Pole Discrepancy Protection. 05/09/2023 09:32 AM Actions
5087 IEC 61850 User Feedback Task Force Feature 11 MH Resolved Normal

IEC 61850-7-4 Ed2.1 ,7-5

Clarifications on the local/remote concept 7/8 06/05/2023 01:58 AM Actions