651 Server Issues New Normal Verify subscriber can accept maximum size GOOSE 03/19/2021 03:27 AM Actions
647 IEC 61850 User Feedback Task Force Support 57 ENTSO-E Resolved Normal

IEC 61850-7-5, IEC61850-7-500

Single phase and multi phase trip indication for the autorecloser 04/13/2021 09:42 AM Actions
636 Client Issues Resolved High Mandate RCB reservation for Ed2.0 client and Amd1 server 04/20/2021 02:23 PM Actions
633 IEC 61850 User Feedback Task Force Improvement 1 ZIV In Progress Normal

IEC 61850-7-2

Initial values of paramRev and valRev 04/13/2021 09:50 AM Actions
632 IEC 61850 User Feedback Task Force Support 8 H30 In Progress High

IEC 61850-9-2, IEC 61869-9

APPID 0x4000 - Sampled Values 06/16/2021 09:42 AM Actions
631 IEC 61850 User Feedback Task Force Feature 44 RTE Triage Normal Evolution of LN PSCH to build switching on information 08/17/2021 08:03 AM Actions
630 IEC 61850 User Feedback Task Force Improvement 43 RTE Resolved Normal

IEC 61850-7-5/7-500

XCBR LN new DO to describe withdrawable circuit breaker 02/09/2022 08:05 AM Actions
629 IEC 61850 User Feedback Task Force Improvement 35 RTE Triage Normal TCTR and TVTR new DO to identify common bay level 06/21/2022 08:20 AM Actions
627 IEC 61850 User Feedback Task Force Feature 29 RTE Resolved Normal

IEC 61850-7-4

Activation and deactivation of a function by configuration. 03/02/2021 09:53 AM Actions
626 IEC 61850 User Feedback Task Force Improvement 23 RTE In Progress Normal

IEC 61850-6

Extension of P-type to describe connexion type (PhysCon) 03/02/2021 09:51 AM Actions
625 IEC 61850 User Feedback Task Force Improvement 22 RTE Resolved Normal

IEC 61850-7-4

LN RADR evolution 03/02/2021 09:49 AM Actions
624 IEC 61850 User Feedback Task Force Support 21 RTE Triage Normal

IEC 61850-6

Clarification of using of ValKind, ValImport. 03/02/2021 09:44 AM Actions
623 IEC 61850 User Feedback Task Force Feature 19 RTE In Progress Normal New LN of group L (as "LPLE") representing a group of LED 03/02/2021 09:42 AM Actions
622 IEC 61850 User Feedback Task Force Feature 18 RTE Triage Normal

IEC 61850-7-4

Parameters not available in standardized LN 06/20/2022 03:56 AM Actions
621 IEC 61850 User Feedback Task Force Feature 17 RTE In Progress Normal

IEC 61850-7-4/7-500

New controllable DO in RREC to define the mode of the recloser of the circuit breaker 05/11/2021 10:08 AM Actions
620 IEC 61850 User Feedback Task Force Feature 16 RTE Triage Normal New LN LPDO / LPDI in IEC 61850-7-5 06/20/2022 03:55 AM Actions
619 IEC 61850 User Feedback Task Force Feature 15 RTE Resolved Normal New LN of group L (as "LTED") to represent the dynamic topology of the substation. 03/02/2021 09:29 AM Actions
618 IEC 61850 User Feedback Task Force Improvement 14 RTE Triage Normal

IEC 61850-90-3

Evolution of DO SumSqA of LN SPTRExt 06/20/2022 03:54 AM Actions
612 IEC 61850 User Feedback Task Force Feature 11 RTE In Progress Normal

IEC 61850-7-4

Need to create a new LN of group P (Protection), as "PCDP" to represent the Pole Discrepancy Protection. 06/21/2022 08:25 AM Actions
611 IEC 61850 User Feedback Task Force Bug 5 RTE In Progress Normal

IEC 61850-7-4 / IEC 61850-80-6

Need a new DO (ENUM) to identify the protocol used for the SCADA exchange, in LN ITCI 05/11/2021 09:59 AM Actions
610 IEC 61850 User Feedback Task Force Improvement 2 RTE Resolved Normal

IEC 61850-6

Mapping of another phases system description to the generic phases phsA, phsB, phsC 05/11/2021 10:13 AM Actions
608 IEC 61850 User Feedback Task Force Feature 7 H30 In Progress Normal

IEC 61850-90-xx

Comprehensive set of requirements covering validation and supervision of all IEC 61850 communications 06/21/2022 02:09 AM Actions
607 IEC 61850 User Feedback Task Force Support 6 H30 In Progress Normal

IEC 61850-80-6 (90-2)

LPHD.Sim management 06/21/2022 02:09 AM Actions
605 IEC 61850 User Feedback Task Force Improvement 4 H30 In Progress Normal

IEC 61850-10-3

Test and Simulation mode questions 06/21/2022 02:09 AM Actions
602 IEC 61850 User Feedback Task Force Feature 1742 IOP_2019 In Progress Normal

IEC 61850-9-3

Merging Unit standard requires MU clock to jump on PTP time jumps, which is not true for Boundary Clocks. 06/21/2022 09:30 AM Actions