Project

General

Profile

Feature #574

Protection scheme: Weak end infeed (1 phase and 2/3 phase operate missing)

Added by Herbert Falk about 3 years ago. Updated over 1 year ago.

Status:
Closed
Priority:
Normal
Assignee:
-
Category:
Standard extension required
Start date:
Due date:
% Done:

0%

Estimated time:
ID:
46
Source:
ENTSO-E
TF Unique ID:
46 # ENTSO-E
WG10 Proposal:
Estimated Completion:
Next meeting in Charlotte - 19/09
Discuss in Upcoming Meeting:
No
To discuss in WG10:
No
Short Proposal:

To revise PSCH LN or to create new LN in protection domain(19-06-06) To create Use-case with different scenarios in order to clearly define scope of application (Vladan C)

Standard(s):

IEC 61850-7-4

Needs More Information:
Yes
Assigned TF:

Description

Protection scheme: Weak end infeed (1 phase and 2/3 phase operate missing)
According to 7-4 there is no operation defined for Week end infeed granulated in such way to have information about 1 phase or 2/3 phases operation.
a) Allocation of WEI is in PSCH.
b) If WeiMod is correctly defined (for example Echo and Operate) then there will be both EchoWei (SPS) and EchoWeiOp (SPS).
c) By logic: AND==True can be retrieved signal required by ENTSO-e : Operate 1 phase by weak end infeed or:
By logic: AND, AND,…., AND), PSCH.EchoWeiOp.stVal )==True can be retrieved signal: Operate 2/3 phase by weak end infeed
d) Question is – how to maintain semantics and not use GGIO to recreate this logical creation of signal for applications such as Gateway TC interface, HMI event list presentation, additional Logic…? Basically, building blocks are there but how to use them in standardized way?

Similar question arise for Distance protection 2/3 phase operate – where logic (for example): OR, AND,…., AND)==True
can result in expected Distance protection 2/3 phase operate but if we follow practice that DA = SCADA signal that this can be identified only as a gap.

Also available in: Atom PDF