Project

General

Profile

CIM Issues #4436

The requirements of individual people, crews and work tasks

Added by Herbert Falk over 2 years ago.

Status:
Closed
Priority:
Normal
Author/Contact Info:
Part 6 & 11 Teams
Base Release:
Solution to be Applied To:
Solution Version:
CIM10
Solution Applied By:
Completion Date:
CIM Keywords:
Breaking Change:
No
Breaking Change Description:
CIM Impacted Groups:
WG13
Requestor:
Standard(s):
Version:
Clause:
Sub-Clause:
Paragraph:
Table:
Originally Closed in Version:
CIM10
Origination Date:
11/20/2005
Origination ID:
136
Originally Assigned To:

Description

The requirements of individual people, crews and work tasks need to be better articulated better, making necessary distinctions as to where and when they apply.


Proposed Solution

In WorkSchedule Package, add Usage class and associate it with MaterialItem and EquipmentAsset. Remove association of WorkTask to QualificationRequirement, since QualificationRequirement is asset related, and replace it with Capability, which is Crew and WorkTask related. In TopLevel Pakcage, add Craft and associate it with ErpPersona and Skill. Add Capability class to Crew Package and associate it with Crew and Craft.


Decision

Proposed change accepted.