Switch status as input to topology processing There is no a

Added by Herbert Falk over 2 years ago.

Status:
Closed
Priority:
Normal
Author/Contact Info:
Lars-Ola Osterlund
Base Release:
61970cim16v18
Solution to be Applied To:
61970cim16v19
Solution Version:
CIM16
Solution Applied By:
LOO
Completion Date:
03/04/2013
CIM Keywords:
Breaking Change:
No
Breaking Change Description:
CIM Impacted Groups:
WG13
Requestor:
Standard(s):
Version:
Clause:
Sub-Clause:
Paragraph:
Table:
Originally Closed in Version:
CIM16
Origination Date:
03/04/2013
Origination ID:
13_135
Originally Assigned To:

Description

Switch status as input to topology processing
There is no attribute telling the switch status that was used as input to topology processing.


Proposed Solution

Add to SwitchPhase as well.
Refer to issue 13_124.