Project

General

Profile

CIM Issues #3936

Substation in Boundary MAS

Added by Herbert Falk over 2 years ago.

Status:
Closed
Priority:
Normal
Author/Contact Info:
ENTSO-E /Lars-Ola O.
Base Release:
61970cim15v03 61968cim11v02
Solution to be Applied To:
Solution Version:
CIM15
Solution Applied By:
LOO
Completion Date:
10/05/2010
CIM Keywords:
Breaking Change:
No
Breaking Change Description:
CIM Impacted Groups:
WG13
Requestor:
Standard(s):
Version:
Clause:
Sub-Clause:
Paragraph:
Table:
Originally Closed in Version:
CIM15
Origination Date:
08/14/2010
Origination ID:
13_17
Originally Assigned To:

Description

Substation in Boundary MAS


Proposed Solution

Necessary discussion in WG13 to find a solution that will serve "operational" and "planning" profiles. Decision points:
- Substation in or not in the boundary
- Is the NodeContainer needed in the
boundary?
- Is a BaseVoltage needed for
boundary nodes? If yes, what the
solution is.


Decision

The following is was decided
. If the border is at a line the boundary node shall be included in a cim:Line. The cim:Line is in the boundary model authority set.
. If the border is within a substation the boundary node shall be included in a cim:Substation. The cim:Substation is in the boundary model authority set.
IEC 61970-452 updated for CIM15.
WG13 meeting Minneapolis 2010-10-05

No data to display